G. E BOOTH WRRF – TOX 3 – DUCTS

By maplevalefab,

This project involves the fabrication of stainless steel and carbon steel ducts, with diameters ranging from 56″ to 72″.

All components, including 90° miters, will be custom-designed and fabricated in-house to ensure quality and precision. The ducts will be bolted to existing pieces, making accuracy critical for seamless integration.

 

Duffin Creek WPCP-Biosolids treatment Replacement Contract 1

By maplevale,

• Extension of existing HWS & HWR pipes to the new heat exchange system in the North Incinerator Facility.
• New Ash Slurry piping.
• High Pressure Steam Piping (TSSA)
• Medium Pressure Steam Piping (TSSA)
• Low Pressure Stam Piping (TSSA)
• Boiler Feed Water Piping (TSSA)
• Sand Silo Piping (TSSA)
• Exhaust Air Piping.

• HWS & HWR Piping.

 

 

DUFFIN CREEK – WATER POLLUTION CONTROL PLANT